UPSSSC PET 2023 (28 Oct Shift 2)
Directions

Which of the following groups take minimum time to complete the work ?
Answer (Detailed Solution Below)View answer ā¾Hide ā“
Answer: Option A ā Chaman and Ramesh
Detailed Solution
The pair with the largest one-day work takes the least time; Chaman + Ramesh .
Other pairs: Rakesh + Axay , Axay + Ramesh , Chaman + Axay ; so Chaman and Ramesh finish fastest, in days.
š¬ Discussions on this question
Ask a doubt āŗStill stuck on this question? Ask our faculty and fellow students ā answers appear here.
Ask a doubtMore Time & Work Questions
View all āŗ- Q1., , are painters. paints a wall of area A in 10 hours; paints the same wall in 20 hours. Together, , and paint an area 2A in 8 hours. How many hours will alone take to paint the wall A?
- Q2.If 15 students can complete a project in 10 days, how many days will it take for 10 students to complete the same project?
- Q3.If 2 cats catch 2 mice in 2 minutes, how many cats are needed to catch 18 mice in 18 minutes?
- Q4.If 6 cats catch 6 mice in 6 minutes, how many cats are needed to catch 36 mice in 18 minutes?
- Q5.A and B can complete a work in 12 days, B and C complete a work in 15 days and C and A can complete a work in 20 days. Find in how many days they all together can complete a work?
More Quantitative Aptitude Questions
- Q1.By selling 45 lemons for ā¹40, a man loses 20%. How many lemons should he sell for ā¹24 to gain 20%?Profit, Loss & Discount
- Q2.The marked price of an article is 1.45 times its cost price. Its selling price is ā¹1,500 and the profit is 25%. What is the discount percentage? Profit, Loss & Discount
- Q3.Let A be a real number. Then the roots of the equation are real and distinct if and only if Quadratic Equations
- Q4.The number of distinct real roots of the equation is Quadratic Equations
- Q5.The roots of are:Quadratic Equations
Time & Work ā UPSSSC PET Preparation
This question tests your understanding of Time & Work, a key topic in the UPSSSC PET Quantitative Aptitude section. The detailed solution above uses a step-by-step approach to show the reasoning, and where available, a shortcut that helps you solve similar questions in under 90 seconds during the actual exam.
Time and work questions deal with how long one or more people, machines or pipes take to complete a task. The core idea is that if someone finishes a job in n days, they complete 1/n of the job each day. Questions involve people working together, joining or leaving partway, working on alternate days, efficiency comparisons, and wages shared in proportion to work done. Pipes and cisterns questions use the same logic and have their own page. The LCM method is the fastest approach for most questions. Take the total work as the LCM of the individual times, find each person's work per day, and the rest becomes simple division. This avoids messy fractions and makes problems with three or more workers much easier to handle. Practise the time and work questions below. Each solution shows the step-by-step working and the LCM shortcut where it helps.